A little cold out there with a game temp around 40* F, our bats started cold with a 0-0 score after 2. Constance Free bats came alive in the 3rd scoring 4 times on our way to a 15-0 win over Meadow Creek. The game highlight came with Jim Blair diving catch of a sure base hit to left, then turning and doubling off the runner at 2nd. A great start to defend our division title from last year. Next up, Horizon's Silver 6:15 Sand Creek #5.

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

3 commentsJoel Friday, e-PRO • April 28 2008 10:04PM

35W River bridge update

Minnesota Deparment of Transportation - Project Updates
I-35W Bridge over the Mississippi
April 28, 2008
Greetings!  
 
Attention: The weekly update will now be distributed at the beginning of the week instead of end of the week. 
 

If you have questions, please do not reply directly to this email. Contact

Amy Barrett, Public Information Officer, at (612) 236-6901 or via e-mail at abarrett@flatironcorp.com.

I-35W Project Observes Workers Memorial Day

The I-35W Project Team will cease work for a short period of time at 2 p.m. today in honor of Workers Memorial Day. Flatiron-Manson Joint Venture is joining Mn/DOT, as well as many other businesses and labor organizations, in this commemoration that takes place on April 28 each year to remember workers who have lost their lives while on the job.

Safety First

Anyone who visits the site will see signs or stickers on hard hats with this, "Safety First" reminder. With seven months of work underway, Flatiron-Manson Joint Venture is proud to report that it has no lost-time injuries and only nine minor reportable incidents in almost 300,000 work hours. Industry average is about nine reportable incidents per 200,000 hours.

Hauling Gets Underway

This week, crews will begin the anticipated hauling of the pre-cast main span segments from the casting yard to Bohemian Flats. Crews will periodically close 13th Avenue South from the casting yard entrance to West River Parkway as they transport pre-cast segments to the river. Hauling operations will take place between 7 a.m. and 7 p.m., seven days a week for up to five weeks. The road will be closed for up to 10 minutes each time a segment is moved.
 
"Big Ben" Assembled

"Big Ben" (pictured below), the name given to the barge-mounted ringer crane that will install the main span segments has been assembled. Testing and final preparations including dropping the anchor to hold the crane in place are being completed in advance of the main span assembly planned for mid-May. 
 

Big Ben

 

Construction Update

 
Work scheduled for the week includes:

 

  • Continuing to work on the pre-cast segments that will eventually span the river. As of last week, crews had built 65 of the 120 necessary segments. Crews plan to build up to 15 segments this week.
  • Pouring concrete for the approach spans on the south side of the river.
  • Continuing construction of the approach spans on the north side of the river.
  • Constructing the abutment for the Second Street bridges on the north side of the project (see below).

Constructing the abutment

  • Beginning excavation work on I-35W road bed on the north side of the project. That excavation work will take place 24 hours a day and should last for about a week.

Area residents and motorists will experience traffic issues as well as some noise and light disruptions in the coming weeks.

 

Potential Traffic Impacts

 

13th Avenue South to be Closed During Hauling Operations - Hauling will run along 13th Avenue South and South Second Street to the river's edge on the south side of the construction site (using the entrance at 13th Avenue South and West River Parkway). Flaggers will be present while hauling is in progress, and traffic attendants will be posted at all driveways along the haul route.

 

Truck Traffic - There will be increased construction traffic in the vicinity of the site. Some of the streets affected include: Second Street Southeast east to 11th Avenue Southeast; Second Street Southeast to Sixth Avenue Southeast,  First Street South and 19th Avenue South, Bluff Street south to 13th Avenue South, Second Street South west to 11th Avenue South.

 

Sidewalk/lane closures at Washington and University - The sidewalk on the north side of Washington Avenue may be closed between Seven Corners and 12th Avenue South while crews redo the curb cuts at the corners. Occasional lane closures may also be necessary during this phase of construction. Similar work will take place on University Avenue between Eighth and 10th avenues SE starting in mid-May.

 

Street Closures Needed at 14th Avenue South and First Street South - To allow utility relocation and widening of I-35W northbound, 14th Avenue South and First Street South (near the Seven Corners Apartments) are temporarily closed. Street parking on Second Street South and 14th Avenue is restricted to allow two-way traffic along Second Street South from 19th Avenue to the closure.
 
10th Avenue Bike Lane Closed - The bike lane on the west side of the 10th Avenue Bridge will be closed until further notice from 11 a.m. until noon on Saturdays - when the weekly Sidewalk Talks are in progress - to ensure the safety of everyone using the bridge. The City of Minneapolis has posted signs noting the restriction at each end of the bridge. Bikes and pedestrians are urged to use the lane on the east side of the bridge between 11 a.m. and noon.

Potential Noise and Light Impacts

 

Crews are working night shifts seven days a week on both sides of the river as well as in the casting yard. Lights and construction traffic may be noticeable between 5:30 p.m. and 4 a.m.

 

As crews begin to relocate utilities and widen the highway on the south side of the construction site, there will be noticeable hammering as they remove the old asphalt, curbs and gutters. Back-up alarms will also be noticeable as trucks are loaded in that area.

 

Hammering noise will accompany falsework construction on the north side of the river.

 
Planning Your Route to Downtown Minneapolis
 - If you are planning to drive to downtown Minneapolis, you can use the links below to plan your route:
 

Help Spread the Word

 

Do you know someone who would appreciate the up-to-date news, first-look pictures and detailed information you get each week? Click on the "Forward email" link at the bottom of this message to pass on a copy of this week's update with an invitation to sign up. 

Getting a Closer Look

Get up-to-the minute updates about progress on the bridge - Jon Chiglo, Mn/DOT Project Manager, will describe what you can expect as the project continues. He'll appear live at 6:10 a.m., Tuesday, April 29 on KSTP-TV, Channel 5.
 
Try the touch-screen kiosks at Mill City Museum and the airport -
Touch-screen kiosks that provide a variety of information about the bridge, including a photo gallery, a timetable and animations showing what the finished bridge will look like from a helicopter, a boat and a car are available in the Mill City Museum lobby and at Concourse C at the Minneapolis-St. Paul International Airport.

Visit the website - The website offers up-to-date information, presentations, graphics, photos and animations, as well as interesting features on workers on the project. You can access the website at www.mndot.gov.

Access the webcams - One provides a panoramic view of the entire construction site, looking east from a rooftop on the north side of the Mississippi River. The other camera is mounted on a light pole on the 10th Avenue Bridge and will provide periodic close-ups of construction activities. To see the webcam views, visit the project website at www.mndot.gov.
 
Attend a Sidewalk Superintendent Talk - These weekly events provide an opportunity to accompany project representatives on a walk across the 10th Avenue Bridge, where you can see the construction workers in action and ask questions about the project. If you'd like to participate, meet in the parking lot in front of Grandma's restaurant at 19th and Washington avenues by 11 a.m. on any Saturday.
 
Take a self-guided tour - Signs describing the design/build process are mounted along the 10th Avenue Bridge.
 
Call the hotline - If you have any questions about the project, please call the hotline at (612) 236-6901 between 7 a.m. and 8 p.m. daily. Messages left after 8 p.m. will be returned first thing the morning of the next business day.
 
Request a presentation - Representatives of Mn/DOT and Flatiron-Manson are willing and eager to provide project updates to neighborhood associations, business associations and other groups. To arrange a presentation, please call the hotline, (612) 236-6901.
 
Other than viewing what's happening from the 10th Avenue Bridge, the public is asked to stay away from the bridge construction area for safety reasons. 
 
The Minnesota Department of Transportation (Mn/DOT) and the Flatiron-Manson construction team intend to build a high quality and safe bridge while minimizing disruptions to the surrounding neighborhoods.
 
We will continue to distribute updates weekly and welcome your comments on how to improve the communication process between the project team and the community.
 
For more information on the I-35W project visit www.mndot.gov
or call the I-35W Bridge Hotline at (612) 236-6901.

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

0 commentsJoel Friday, e-PRO • April 28 2008 06:21PM

Hanson Blvd blast

Hanson Blvd reconstruction kicks off in full force on Monday, according to the flashing signs. This road will be a mess until the construction is completed in August. Use other routes as the intersections at 14 and Bunker will rebuilt. Traffic already is at a stand still at rush hour and will only get worse.

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

0 commentsJoel Friday, e-PRO • April 25 2008 05:48PM

Crosstown Blues, not so blue

Note Hwy 62 will remain open this weekend but 35W will be closed from 62 to 94. 

 

Minnesota Department of Transportation

 

 

Crosstown: I-35W/Hwy 62 Reconstruction
April 25, 2008
Dear Joel Friday,
 
This is an update on the Crosstown project. If you have questions, please do not reply directly to this email.  Please visit http://www.dot.state.mn.us/projects/crosstown/ and click on "Project Contacts."

Freeway ramp, road to close at Lyndale Avenue/Highway 62 on April 29-30

ROSEVILLE, Minn. - The exit ramp from westbound Highway 62 to Lyndale Avenue is scheduled to close from 9 p.m. to 5 a.m. on Tuesday, April 29 and Wednesday, April 30.

In addition to the ramp closure, Lyndale Avenue South at I-35W/Highway 62 is also scheduled to close during the same time frame.

The closures are needed to conduct bridge work in the area as part of the I-35/Highway 62 Crosstown reconstruction project.

Motorists should follow the posted detours routes.

I-35W and Highway 62 will remain open during closures; however, in conjunction with the bridge work, there will be a right lane closure of westbound Highway 62 at the Lyndale Ave bridge area.

For more information on the I-35W/Hwy 62 Crosstown Reconstruction project, visit www.mndot.gov or call the Crosstown Project hotline at 1-866/743-6590 or send an e-mail to crosstown@rranow.com.

Mn/DOT reminds motorists to slow down in work zones and never enter a roadway that has been blocked with barriers or cones. For statewide traffic, construction and travel information visit www.511mn.org or call 511 or log onto www.mndot.gov

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

0 commentsJoel Friday, e-PRO • April 25 2008 05:38PM

35W river bridge progress

Minnesota Deparment of Transportation - Project Updates
I-35W Bridge over the Mississippi
April 22, 2008
Greetings!  
 
Attention: The weekly update will now be distributed at the beginning of the week instead of end of the week. 
 

If you have questions, please do not reply directly to this email. Contact

Amy Barrett, Public Information Officer, at (612) 236-6901 or via e-mail at abarrett@flatironcorp.com.

Open House at University of Minnesota's Coffman Memorial Union

 
The University of Minnesota Student Chapter of the American Society of Civil Engineers is hosting Mn/DOT and the Flatiron-Manson Joint Venture for an Open House this Thursday, April 24 at Coffman Memorial Union on the University of Minnesota campus. This is an opportunity for those who are interested in the project to receive updates on the bridge's progress.
 

Thursday, April 24
11 a.m.-1 p.m.

Coffman Memorial Union on the University of Minnesota Campus

Table on the Ground Floor, Outside of the Cafeteria and Great Hall
300 Washington Avenue SE
Minneapolis, MN 55455

(across Washington Avenue SE from Northrop Mall)
For a map of the location go to:
http://www1.umn.edu/twincities/maps/CMU/CMU-map.html
 

Barges Arrive and Pre-Cast Segments More than Half Complete

 

The two barges that will support the ringer crane used to place main span segments arrived at Bohemian Flats on Saturday, April 12. The barges have been moved up river and are now anchored near Pier 3 in preparation for the main span assembly.  

 
As of last week, crews had poured 61 of the 120 segments needed for the main span and expect to pour another 12 segments this week. Later this week, workers will begin hauling the pre-cast segments from the casting yard to Bohemian Flats. From that location, they will be loaded onto the barges by Bohemian Blue (the blue crane pictured below) to be transported up river to the bridge site and lifted into place by Big Ben (the red crane). This work will begin the first week in May.

Bohemian Blue

 

Construction Update

 

Work scheduled for the week includes:

  • Continuing to work on the pre-cast segments that will eventually span the river.
  • Assembling the barge mounted ringer crane that will install segments.
  • Pouring concrete for the approach spans on the south side of the river.
  • Constructing the abutment for the Second Street bridges on the north side of the project.

Area residents and motorists will experience traffic issues as well as some noise and light disruptions in the coming weeks.

 
Placing Rebar
 
Work continues on the south approach span of the new bridge (above). Workers are placing rebar and preparing the forms so they can continue pouring concrete during the coming weeks.
 
Potential Noise Impacts
 
Crews will work several nights each week at the Minneapolis Cemstone concrete plant. Neighborhood residents may hear back-up alarms and other noise related to trucks loading and unloading. Cemstone officials have said they will attempt to minimize the noise.
 
As crews begin to relocate utilities and widen the highway on the south side of the construction site, there will be noticeable hammering as they remove the old asphalt, curbs and gutters. Back-up alarms will also be noticeable as trucks are loaded in that area.
 
Hammering noise will accompany falsework construction on the north side of the river.
 
Potential Light Impacts
 
Crews are working night shifts seven days a week on both sides of the river as well as in the casting yard. Lights may be noticeable between 5:30 p.m. and 4 a.m.
 
Potential Traffic Impacts
 
13th Avenue South to be Closed During Hauling Operations - Also starting this week, crews will close 13th Avenue South for up to 10 minutes at a time, several times a day, to haul pre-cast concrete segments from the casting yard exit (at 13th Avenue South and South Second Street) to the river's edge on the south side of the construction site (using the entrance at 13th Avenue South and West River Parkway). Crews plan to transport up to six segments a day, at a rate of approximately one segment every two hours. Hauling will take place between 7 a.m. and 7 p.m. seven days a week until about June 1. Flaggers will be present while hauling is in progress, and traffic attendants will be posted at all driveways along the haul route.
 
Sidewalk/lane closures at Washington and University - Starting this week, the sidewalk on the north side of Washington Avenue may be closed between Seven Corners and 12th Avenue South while crews redo the curb cuts at the corners. Occasional lane closures may also be necessary during this phase of construction. Similar work will take place on University Avenue between Eighth and 10th avenues SE starting in mid-May.
 
Street Closures Needed at 14th Avenue South and First Street South - To allow utility relocation and widening of I-35W northbound, 14th Avenue South and First Street South (near the Seven Corners Apartments) are temporarily closed. Street parking on Second Street South and 14th Avenue is restricted to allow two-way traffic along Second Street South from 19th Avenue to the closure.
 
10th Avenue Bike Lane Closed - The bike lane on the west side of the 10th Avenue Bridge will be closed until further notice from 11 a.m. until noon on Saturdays--when the weekly Sidewalk Talks are in progress--to ensure the safety of everyone using the bridge. The City of Minneapolis has posted signs noting the restriction at each end of the bridge. Bikes and pedestrians are urged to use the lane on the east side of the bridge between 11 a.m. and noon.
 
Truck Traffic - Trucks will be departing from the construction site regularly. Truck traffic is likely on the following routes: on Second Street Southeast east to 11th Avenue Southeast; west on Second Street Southeast to Sixth Avenue Southeast, north on Sixth Avenue and then east on University Avenue; on First Street South and 19th Avenue South; from Bluff Street south on 13th Avenue South, west on Second Street South then west on 11th Avenue South.

Planning Your Route to Downtown Minneapolis - If you are planning to drive to downtown Minneapolis, you can use the links below to plan your route:
 

Help Spread the Word

 

Do you know someone who would appreciate the up-to-date news, first-look pictures and detailed information you get each week? Click on the "Forward email" link at the bottom of this message to pass on a copy of this week's update with an invitation to sign up. 

Getting a Closer Look

Get up-to-the minute updates about progress on the bridge - Jon Chiglo, Mn/DOT Project Manager, will describe what you can expect as the project continues. He'll appear live at 6:10 a.m., Monday, April 28 on KSTP-TV, Channel 5.
 
Try the touch-screen kiosks at Mill City Museum and the airport -
Touch-screen kiosks that provide a variety of information about the bridge, including a photo gallery, a timetable and animations showing what the finished bridge will look like from a helicopter, a boat and a car are available in the Mill City Museum lobby and at Concourse C at the Minneapolis-St. Paul International Airport.

Visit the website - The website offers up-to-date information, presentations, graphics, photos and animations, as well as interesting features on workers on the project. You can access the website at www.mndot.gov.

Access the webcams - One provides a panoramic view of the entire construction site, looking east from a rooftop on the north side of the Mississippi River. The other camera is mounted on a light pole on the 10th Avenue Bridge and will provide periodic close-ups of construction activities. To see the webcam views, visit the project website at www.mndot.gov.
 
Attend a Sidewalk Superintendent Talk - These weekly events provide an opportunity to accompany project representatives on a walk across the 10th Avenue Bridge, where you can see the construction workers in action and ask questions about the project. If you'd like to participate, meet in the parking lot in front of Grandma's restaurant at 19th and Washington avenues by 11 a.m. on any Saturday.
 
Take a self-guided tour - Signs describing the design/build process are mounted along the 10th Avenue Bridge.
 
Call the hotline - If you have any questions about the project, please call the hotline at (612) 236-6901 between 7 a.m. and 8 p.m. daily. Messages left after 8 p.m. will be returned first thing the morning of the next business day.
 
Request a presentation - Representatives of Mn/DOT and Flatiron-Manson are willing and eager to provide project updates to neighborhood associations, business associations and other groups. To arrange a presentation, please call the hotline, (612) 236-6901.
 
Other than viewing what's happening from the 10th Avenue Bridge, the public is asked to stay away from the bridge construction area for safety reasons. 
 
The Minnesota Department of Transportation (Mn/DOT) and the Flatiron-Manson construction team intend to build a high quality and safe bridge while minimizing disruptions to the surrounding neighborhoods.
 
We will continue to distribute updates weekly and welcome your comments on how to improve the communication process between the project team and the community.
 
For more information on the I-35W project visit www.mndot.gov
or call the I-35W Bridge Hotline at (612) 236-6901.

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

0 commentsJoel Friday, e-PRO • April 22 2008 08:08PM

Crosstown Blues ugly weekend 8^(

Crosstown: I-35W/Hwy 62 Reconstruction
April 22, 2008
Dear Joel Friday,
 
This is an update on the Crosstown project. If you have questions, please do not reply directly to this email.  Please visit http://www.dot.state.mn.us/projects/crosstown/ and click on "Project Contacts."

 

 

46th Street bridge to close on April 25

ROSEVILLE, Minn. - As part of the Interstate 35W/Highway 62 Crosstown reconstruction project, the 46th Street bridge is scheduled to be demolished the weekend of April 25.

To prepare for the bridge demolition, lane closures on the bridge will occur from 9:00 a.m. to 3:00 p.m. on Wednesday, April 23 and Thursday, April 24. The bridge will close at 9:00 a.m. on Friday, April 25. The 46th Street bridge is scheduled to re-open in summer 2009.

The 46th Street intersections of Stevens Ave and 2nd Ave will remain open; however, the intersections will close once bridge reconstruction impacts these areas.

The 46th Street bridge demolition and removal will occur in conjunction with a weekend closure of I-35W: all lanes of northbound I-35W, from Interstate 494 to Interstate 94, and all lanes of southbound I-35W, from I-94 to Hwy 62, will be closed at 10 p.m. Friday, April 25 through 5 a.m. Monday, April 28.

Motorists should follow the posted detours during the closure.

For more information on the I-35W/Hwy 62 Crosstown Reconstruction project, visit www.mndot.govor call the Crosstown Project hotline at 1-866-743-6590 or send an e-mail to crosstown@rranow.com.

 

Mn/DOT reminds motorists to slow down in work zones and never enter a roadway that has been blocked with barriers or cones. For statewide traffic, construction and travel information visit www.511mn.org or call 511 or log onto www.mndot.gov.< /p>

 

 

**************************************************************************************************************

For More Information on the Crosstown Project

Crosstown Project Hotline: 1.866.743.6590

Email: crosstown@rranow.com

Website: www.mndot.gov

Crosstown Project Office: 6242 Lyndale Ave S, Richfield*

*For office hours, call the Crosstown Project Hotline.

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

0 commentsJoel Friday, e-PRO • April 22 2008 08:00PM

Crosstown Blues

Weekly Update

For the week of April 21, 2008

 

Public Information Events

 

Crosstown staff will be available to answer questions about the project at the following location:

 

Bachman's

6010 Lyndale Ave S, Minneapolis

Saturday, May 3, 2008

Crosstown staff available from 10:00 am to 12:00 pm

 

General Updates

 

Northbound I-35W Exit Ramp to Westbound Hwy 62/58th Street Closure: April 21 and 22

The exit ramp from northbound I-35W to westbound Hwy 62/58th Street will be closed from 9 am to 2 pm on Monday, April 21 and Tuesday, April 22. The closure of the exit ramp is needed for sheet piling removal in the area. The ramp closure is being done during daytime hours rather than at night to avoid nighttime noise activity Motorists should follow the posted detour routes. Southbound Hwy 121 with access to southbound I-35W and westbound Hwy 62 will remain open during the closures.

 

I-35W Closure: April 25-28

All lanes of northbound I-35W, from I-494 to I-94, and all lanes of southbound I-35W, from I-94 to Hwy 62, will be closed from approximately 10 p.m. Friday, April 25 through 5 a.m. Monday, April 28. Construction activities during this closure include the demolition of the 46th Street bridge, bridgework at 50th Street and utility work across the freeway at Diamond Lake Road and 46th Street. Motorists can use I-494, Hwy 100 and I-394 to detour around the closure.

 

Hwy 62 Closure: April 25-28

In conjunction with the I-35W weekend closure, Hwy 62 between Penn Ave and the western junction of I-35W is scheduled to close from 10:00 pm Friday, April 25 to 5:00 am Monday, April 28. The freeway closure is needed to conduct utility work across Hwy 62. Motorists can use Hwy 100, I-494 and Hwy 77 to detour around the closure.

 

46th Street Bridge to Close on April 25

The 46th Street bridge is scheduled to be demolished theweekend of April 25. To prepare for the bridge demolition, lane closures on the bridge will occur from 9 am to 3 pm on Wednesday, April 23 and Thursday April 24; and the bridge is schedule to close at 9:00 am on Friday, April 25. The 46th Street intersections of Stevens Ave and 2nd Ave will remain open; however, the intersections will close once bridge reconstruction begins to impact these areas. The 46th Street bridge is scheduled to re-open in summer 2009.

 

I-35W and Hwy 62 Nighttime Lane Closures

Watch for nighttime lane closures on I-35W and Hwy 62 between 9:30 pm and 6 am each night work as work continues throughout the project area.  For up-to-date information on highway construction, traffic, detours and delays call 511 or go to www.511mn.org.

 

Freeway Ramp Closures

The following ramps are closed or tentatively scheduled to close:

 

Lyndale Ave

Lyndale Ave exit ramp from westbound Hwy 62 to Lyndale Ave S

Approximate closure date: Early May 2008

Approximate re-opening: September 2009

 

 

 

Lyndale Ave entrance ramp to eastbound Hwy 62/northbound I-35W

Status: Closed

Approximate re-opening: September 2009

 

Lyndale Ave exit ramp from eastbound Hwy 62 to Lyndale Ave S

Status:  Closed

Approximate re-opening: September 2009

 

Penn Ave

Penn Ave entrance ramp to eastbound Hwy 62

Status:  Closed

Approximate re-opening: July 2009

 

46th Street

46th Street exit ramp from southbound I-35W

Status: Closed

Approximate re-opening: October 2009

 

46th Street entrance ramp to southbound I-35W

Status: Closed

Approximate re-opening: October 2009

 

46th Street exit ramp from northbound I-35W

Status: Closed

Approximate re-opening: October 2010

 

46th Street entrance ramp to northbound I-35W

Status: Closed

Approximate re-opening: October 2010

 

66th Street

66th Street entrance ramp to northbound I-35W

Status: Closed

Approximate re-opening: June 2010

 

Portland Ave

Portland Ave exit ramp from eastbound Hwy 62

Status: Closed

Approximate re-opening: Fall 2008

 

Project Areas

Penn Ave Area

Traffic on eastbound Hwy 62 between Penn Ave and the junction of I-35W has been rerouted to travel along westbound lanes of Hwy 62. Excavation of the "old" lanes of eastbound Hwy 62 continues.

 

Penn Ave entrance ramp to eastbound Hwy 62: Closed

The Penn Ave entrance ramp to eastbound Hwy 62 is closed. The ramp is scheduled to reopen in July 2009.

 

Western Junction of I-35W and Hwy 62

Bridge work at the western junction of I-35W and Hwy 62 continues. Daytime construction activities next week include pile driving.

 

Northbound I-35W Exit Ramp to Westbound Hwy 62/58th Street Closure: April 21 and 22

The exit ramp from northbound I-35W to westbound Hwy 62/58th Street will be closed from 9 a.m. to 2 p.m. on Monday, April 21 and Tuesday, April 22. The closure of the exit ramp is needed for sheet piling removal in the area. The ramp closure is being done during daytime hours rather than at night to avoid nighttime noise activity. Southbound Hwy 121 with access to southbound I-35W and westbound Hwy 62 will remain open during the closures.

 

Hwy 121 Area

Bridge work in the area continues.

 

Lyndale Ave Bridge Area

Construction activities continue around the Lyndale Ave bridge area. To accommodate utility work in the area, Lyndale Ave at Crosstown will continue to be one lane in each direction through the end of April.

 

Lyndale Ave Freeway Ramps

§         The Lyndale Avenue exit ramp from westbound Hwy 62/southbound I-35W remains open, but is scheduled to close in early May 2008.

§         The Lyndale Ave exit from eastbound Hwy 62 is closed. 

§         The Lyndale Avenue entrance ramp to eastbound Hwy 62/northbound I-35W is closed.

 

Soo Railroad (between Lyndale Ave S and Nicollet Ave S)

Bridge work continues.

 

Nicollet Ave Bridge Area

Bridge work continues.

 

Eastern Junction of I-35W and Hwy 62

Bridge work at the eastern junction of I-35W and Hwy 62 continues.

 

Portland Ave Bridge Area

Retaining wall construction activities continue.

 

Portland Ave exit ramp from eastbound Hwy 62: Closed

The Portland Avenue exit ramp fromeastbound Highway 62 is closed. The ramp closure is needed for crews to conduct retaining wall construction. The ramp will re-open by fall 2008.

 

60th Street Bridge Area

Construction activities continue around the 60th Street bridge area. Daytime construction activities next week include pile driving. 60th Street is schedule to close in the evening from 9 pm to 5am on Monday, April 21 and Tuesday, April 22. The 60th Street freeway ramps and I-35W will remain open during the closure. Motorists should follow the posted detours routes. Nighttime activities between 9 pm and 5 am will occur on Monday, April 21 and Tuesday, April 22.

 

Diamond Lake Road Bridge Area

The Diamond Lake Road bridge and all freeway ramps are available. However, short-term closures over the next couple of months may be needed to complete remaining work in the area. Sidewalks on Diamond Lake Road bridge remain closed and are scheduled to re-open in early summer 2008. Pedestrian access is available at 60th Street and Minnehaha Parkway.

 

Minnehaha Parkway Bridge Area

Bridge construction at Minnehaha Parkway and southbound I-35W continues. The construction activities will not impact traffic on I-35W.The bridge construction requires that Minnehaha Parkway be closed through April 25, 2008 (see Neighborhood Updates for more details). 

 

50th Street Bridge Area

Reconstruction of the 50th Street bridge continues. Crews continue to remove the old bridge abutment on the west side. Construction of the new bridge abutment will begin soon; activities include excavation and sheet piling. During the I-35W closure from April 25-28, bridge beams will be set on the eastern portion of the bridge. The 50th Street bridge is tentatively scheduled to re-open in fall 2008.

 

46th Street Bridge Area

The 46th Street bridge is scheduled to be demolished theweekend of April 25. To prepare for the bridge demolition, lane closures on the bridge will occur from 9 am to 3 pm on Wednesday, April 23 and Thursday April 24; and the bridge is schedule to close at 9:00 am on Friday, April 25. The 46th Street intersections of Stevens Ave and 2nd Ave will remain open; however, the intersections will close once bridge reconstruction begins to impact these areas. The 46th Street bridge is scheduled to re-open in summer 2009.

 

46th Street Freeway Ramps: Closed

All freeway ramps at 46th Street are closed. Ramps are scheduled to re-open in 2009 and 2010.

 


Neighborhood Updates

 

Road Closures

60th Street at I-35W

60th Street at I-35W is scheduled to close in the evening from 9 pm to 5 am on Monday, April 21and Tuesday, April 22. The closure is needed to transfer fill from the southwest corner of the 60th Street bridge area to the northwest corner. The 60th Street freeway ramps and I-35W will remain open during the 60th Street closure. Motorists should follow the posted detours routes.

 

Minnehaha Parkway at I-35W Closure Extended

The closure of Minnehaha Parkway at I-35W has been extended until Friday, April 25. The extended closure is needed so that crews can continue to work on bridge construction near Minnehaha Parkway for the widening of southbound I-35W. Minnehaha Parkway is expected to re-open prior to the removal of the 46th Street bridge, which is tentatively scheduled for weekend of April 25. Motorists can cross I-35W at 42nd Street, 46th Street, Diamond Lake Road and 60th Street. During the closure, at least one pedestrian or bike path along Minnehaha Creek at I-35W will remain open; however, the path may be intermittently closed to safely conduct work.

 

Nighttime Construction Activities

Nighttime construction activities are needed in order to complete the project work within schedule and when lane closures on the freeways are allowed.The following areas are scheduled to have nighttime construction activities in the upcoming week between 10 pm and 6 am:

 

Hwy 62 between Penn Ave and I-35W

Activities: Excavation and utility work

Duration: April 25-28

 

Minneapolis

60th Street Bridge Area

Activities: Hauling of dirt

Duration: April 21 and April 22

 

46th Street Bridge Area

Activities: Bridge demolition and removal

Duration: April 25-28

 

Westbound Hwy 62 between Portland Ave and 2nd Ave

Activities: Backfilling of retaining wall

Duration: through May

 

Westbound Hwy 62 between Lyndale Ave and Dupont Ave

Activities: Backfilling of retaining wall

Duration: through May

 

Northbound I-35W between 50th Street and 46th Street

Activities: Excavation and hauling

Duration: intermittently through the summer

 

Southbound I-35W between 46th Street and Minnehaha Creek

Activities: Excavation and hauling

Duration: intermittently through the summer

 

Richfield

Eastbound Hwy 62 between Pleasant Ave and Portland Ave

Activities: Excavation and hauling

Duration: through June

 

Pile Driving

Daytime pile driving continues to occur throughout the project. Pile driving may occur between 6 am and 6 pm. In the upcoming week, pile driving will occur in the following areas:

 

Western Junction of I-35W

Duration: through early May

 

Minneapolis

60th Street and I-35W

Duration: through early May

 

Noise Wall Demolition

Existing noise walls along the Crosstown Project areas are being be taken down. Understanding the importance of the noise walls for neighborhoods, existing noise walls will be kept in place as long as possible and construction of new noise walls will be done as quickly as possible.

 

The following noise walls are scheduled to be removed:

 

Location: Along southbound I-35W near Stevens Avenue between 51st Street and Minnehaha Creek.

Approximate removal: Week of April28

 

Road Changes

Lyndale Ave at Crosstown

To accommodate utility work in the area, Lyndale Ave at Crosstown will continue to be one lane in each direction through the end of April.

 

Stevens Ave from 45th Street to 50th Street*

To facilitate construction activities, including retaining wall construction, Stevens Ave from 45th Street to 50th Street has been changed to a one-way, one lane road going south.

 

2nd Ave from 50th Street to 42nd Street*

To facilitate construction activities, including retaining wall construction, 2nd Ave from 50th Street to 42nd Street has been changed to a one-way, one lane road going north.

 

*Concrete barriers are placed in the roadway to protect residents and motorists from construction activities. The barriers will be in place until construction activities are complete. Because of the road width reduction, parking along the construction zone is not allowed.

 
 

**************************************************************************************************************

For More Information on the Crosstown Project

Crosstown Project Hotline: 1.866.743.6590

Email: crosstown@rranow.com

Website: www.mndot.gov

Crosstown Project Office: 6242 Lyndale Ave S, Richfield*

*For office hours, call the Crosstown Project Hotline.

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

0 commentsJoel Friday, e-PRO • April 18 2008 05:49PM

Crosstown Blues

From MNDOT 
 
Crosstown: I-35W/Hwy 62 Reconstruction
April 14, 2008
This is an update on the Crosstown project. If you have questions, please do not reply directly to this email.  Please visit http://www.dot.state.mn.us/projects/crosstown/ and click on "Project Contacts."

Weekly Update

For the week of April 14, 2008

 

Public Information Events

 

Crosstown staff will be available to answer questions about the project at the following event:

 

Kenny Neighborhood Meeting

Tuesday, April 15

7:00 pm

AnthonyMiddle School

5757 Irving Ave S, Minneapolis

 

General Updates

 

I-35W Closure: April 25-28

A closure of I-35W between I-94 and Hwy 62 is scheduled from 10:00 pm Friday, April 25 to 5:00 am Monday, April 28; weather permitting.  Construction activities during this closure include the demolition of the 46th Street bridge, bridgework at 50th Street and utility work across the freeway at Diamond Lake Road and 46th Street.

 

46th Street Bridge to Close on April 25

The 46th Street bridge remains open; however, the bridge is scheduled to be demolished theweekend of April 25; weather permitting.  In preparation for the bridge demolition, the 46th Street bridge will be closed at 9:00 am on Friday, April 25. The 46th Street bridge is scheduled to re-open in spring 2009.

 

Upcoming Hwy 62 Weekend Closure

A weekend closure of Hwy 62 between Penn Ave and the western junction of I-35W is tentatively scheduled for early May.  The freeway closure is needed to conduct utility work across Hwy 62. More details to follow in upcoming updates.

 

I-35W and Hwy 62 Nighttime Lane Closures

Occasional nighttime lane closures on I-35W and Hwy 62 between 9:30 pm and 6 am may occur.For up-to-date information on highway construction, traffic, detours and delays call 511 or go to www.511mn.org.

 

Freeway Ramp Closures

The following ramps are closed or tentatively scheduled to close:

 

Lyndale Ave

Lyndale Ave exit ramp from westbound Hwy 62 to Lyndale Ave S

Approximate closure date: Early May 2008

Approximate re-opening: September 2009

 

Lyndale Ave entrance ramp to eastbound Hwy 62/northbound I-35W

Status: Closed

Approximate re-opening: September 2009

 

Lyndale Ave exit ramp from eastbound Hwy 62 to Lyndale Ave S

Status:  Closed

Approximate re-opening: September 2009

 

Penn Ave

Penn Ave entrance ramp to eastbound Hwy 62

Status:  Closed

Approximate re-opening: July 2009

 

46th Street

46th Street exit ramp from southbound I-35W

Approximate closure date: Closed

Approximate re-opening: October 2010

 

46th Street entrance ramp to southbound I-35W

Status: Closed

Approximate re-opening: October 2010

 

46th Street exit ramp from northbound I-35W

Approximate closure date: Closed

Approximate re-opening: October 2009

 

46th Street entrance ramp to northbound I-35W

Status: Closed

Approximate re-opening: October 2009

 

66th Street

66th Street entrance ramp to northbound I-35W

Status: Closed

Approximate re-opening: June 2010

 

Portland Ave

Portland Ave exit ramp from eastbound Hwy 62

Status: Closed

Approximate re-opening: Fall 2008

 

Project Areas

Penn Ave

Traffic on eastbound Hwy 62 between Penn Ave and the junction of I-35W has been rerouted to travel along westbound lanes of Hwy 62. Pavement demolition of the "old" lanes of eastbound Hwy 62 continue through the end of next week.

 

Penn Ave entrance ramp to eastbound Hwy 62: Closed

The Penn Ave entrance ramp to eastbound Hwy 62 is closed. The ramp is scheduled to reopen in July 2009.

 

Western Junction of I-35W and Hwy 62

Bridge work at the western junction of I-35W and Hwy 62 continues.

 

Hwy 121

Bridge work in the area continues.

 

LyndaleAveBridge Area

Construction activities continue around the Lyndale Ave bridge area. Daytime construction activities next week include pile driving. To accommodate utility work in the area, Lyndale Ave at Crosstown will continue to be one lane in each direction through the end of April.

 

Lyndale Ave Freeway Ramps

§         The Lyndale Avenue exit ramp from westbound Hwy 62/southbound I-35W remains open, but is scheduled to close in early May 2008.

§         The Lyndale Ave exit from eastbound Hwy 62 is closed. 

§         The Lyndale Avenue entrance ramp to eastbound Hwy 62/northbound I-35W is closed.

 

Bridge Work at Soo Railroad (between Lyndale Ave S and Nicollet Ave S)

Bridge work continues.

 

NicolletAveBridge Area

Bridge work continues.

 

Eastern Junction of I-35W and Hwy 62

Bridge work at the eastern junction of I-35W and Hwy 62 continues.

 

 

 

PortlandAveBridge Area

Retaining wall construction activities continue.

 

Portland Ave exit ramp from eastbound Hwy 62: Closed

The Portland Avenue exit ramp fromeastbound Highway 62 is closed. The ramp closure is needed for crews to conduct retaining wall construction. The ramp will re-open by fall 2008.

 

60th Street Bridge Area

Construction activities resume around the 60th Street bridge area. Daytime construction activities next week include pile driving. Nighttime activities between 10 pm and 6am may occur for a few nights during the week of April 21. Nighttime construction activities require that 60th Street be closed (see Road Closures under Neighborhood Updates for more details).

 

DiamondLakeRoadBridge and Ramps Open

The Diamond Lake Road bridge and all freeway ramps are available. However, short-term closures over the next couple of months may be needed to complete remaining work in the area. Sidewalks on Diamond Lake Road bridge remain closed and are scheduled to re-open in early summer 2008. Pedestrian access is available at 60th Street and Minnehaha Parkway.

 

MinnehahaParkwayBridge Area

Bridge construction at Minnehaha Parkway and southbound I-35W continues. The construction activities will not impact traffic on I-35W.The bridge construction requires that Minnehaha Parkway be closed through April 18, 2008 (see Neighborhood Updates for more details). 

 

50th Street Bridge Area

Work on the 50th Street bridge resumes. Next week, crews will remove the old bridge abutment on the west side and then begin construction of the new abutment. Pile driving in the area may begin in early May. During the I-35W closure scheduled from April 25-28, bridge beams will be set on the eastern portion of the bridge. The 50th Street bridge is tentatively scheduled to re-open in fall 2008.

 

46th Street Bridge Area

The 46th Street bridge remains open. Daytime construction activities next week include excavating and grading for retaining wall construction. The 46th Street bridge is scheduled to be removed the weekend of April 25; weather permitting. In preparation for the bridge demolition, the 46th Street bridge will be closed at 9:00 am on Friday, April 25. The bridge is tentatively scheduled to re-open in spring 2009.

 

46th Street Freeway Ramps: Closed

All freeway ramps at 46th Street are closed. Ramps are scheduled to re-open in 2009 and 2010.

 

Neighborhood Updates

 

Road Closures

60th Street at I-35W

60th Street at I-35W is tentatively scheduled to close for a few nights during the week of April 21. More details to follow in upcoming updates. The closure is needed to transfer fill from the southwest corner of the 60th Street bridge area to the northwest corner.

 

Minnehaha Parkway at I-35W Closure Extended

The closure of Minnehaha Parkway at I-35W has been extended until Friday, April 25. The extended closure is needed so that crews can continue to work on bridge construction near Minnehaha Parkway for the widening of southbound I-35W. Minnehaha Parkway is expected to re-open prior to the removal of the 46th Street bridge, which is tentatively scheduled for weekend of April 25. Motorists can cross I-35W at 42nd Street, 46th Street, Diamond Lake Road and 60th Street. During the closure, at least one pedestrian or bike path along Minnehaha Creek at I-35W will remain open; however, the path may be intermittently closed to safely conduct work.

 

 

 

 

 

Pile Driving

Daytime pile driving continues to occur throughout the project. Pile driving may occur between 6 am and 6 pm. In the upcoming week, pile driving will occur in the following areas:

 

Minneapolis

Northwest corner of 60th Street and I-35W

Duration: One to two days

 

Richfield

Southeast corner of Lyndale Ave and Crosstown

Duration: through April

 

Noise Wall Demolition

Existing noise walls along the Crosstown Project areas are being be taken down. Understanding the importance of the noise walls for neighborhoods, existing noise walls will be kept in place as long as possible and construction of new noise walls will be done as quickly as possible.

 

The following noise walls are scheduled to be removed:

 

Location: Along southbound I-35W near Stevens Avenue between 51st Street and Minnehaha Creek.

Approximate removal: Week of April21

 

Road Changes

Lyndale Ave at Crosstown

To accommodate utility work in the area, Lyndale Ave at Crosstown will continue to be one lane in each direction through the end of April.

 

Stevens Ave from 45th Street to 50th Street*

To facilitate construction activities, including retaining wall construction, Stevens Ave from 45th Street to 50th Street has been changed to a one-way, one lane road going south. Pavement demolition of the closed portion of Stevens Ave continues through the end of next week.

 

2nd Ave from 50th Street to 42nd Street*

To facilitate construction activities, including retaining wall construction, 2nd Ave from 50th Street to 42nd Street has been changed to a one-way, one lane road going north.

 

*Concrete barriers are placed in the roadway to protect residents and motorists from construction activities. The barriers will be in place until construction activities are complete. Because of the road width reduction, parking along the construction zone is not allowed.

 

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

0 commentsJoel Friday, e-PRO • April 14 2008 01:56PM

Construction in full swing in Blaine

The highway 65 and county road 14 bridge project already has county 14 closed at highway 65 until late August. Detours around the area are posted to use Highway 10. That is a long way out of your way. I suggest Bunker Lake Blvd. to the north and county 12 (109th Ave) to the south.

Hanson Blvd construction in Coon Rapids and Andover will start up shortly to make Hanson a 4 lane highway from County 14 past Bunker Lake Blvd. 

Make sure your home is

"SOLD by Friday!"

Joel Friday

612-868-6287

Andover MN homes for sale

0 commentsJoel Friday, e-PRO • April 07 2008 08:39PM