Softball season began tonight
35W River bridge update
| I-35W Bridge over the Mississippi April 28, 2008 |
| Greetings! Attention: The weekly update will now be distributed at the beginning of the week instead of end of the week. If you have questions, please do not reply directly to this email. Contact Amy Barrett, Public Information Officer, at (612) 236-6901 or via e-mail at abarrett@flatironcorp.com. |
| I-35W Project Observes Workers Memorial Day The I-35W Project Team will cease work for a short period of time at 2 p.m. today in honor of Workers Memorial Day. Flatiron-Manson Joint Venture is joining Mn/DOT, as well as many other businesses and labor organizations, in this commemoration that takes place on April 28 each year to remember workers who have lost their lives while on the job. Safety First Anyone who visits the site will see signs or stickers on hard hats with this, "Safety First" reminder. With seven months of work underway, Flatiron-Manson Joint Venture is proud to report that it has no lost-time injuries and only nine minor reportable incidents in almost 300,000 work hours. Industry average is about nine reportable incidents per 200,000 hours. Hauling Gets Underway This week, crews will begin the anticipated hauling of the pre-cast main span segments from the casting yard to Bohemian Flats. Crews will periodically close 13th Avenue South from the casting yard entrance to West River Parkway as they transport pre-cast segments to the river. Hauling operations will take place between 7 a.m. and 7 p.m., seven days a week for up to five weeks. The road will be closed for up to 10 minutes each time a segment is moved. "Big Ben" (pictured below), the name given to the barge-mounted ringer crane that will install the main span segments has been assembled. Testing and final preparations including dropping the anchor to hold the crane in place are being completed in advance of the main span assembly planned for mid-May.
|
|
Construction Update
Area residents and motorists will experience traffic issues as well as some noise and light disruptions in the coming weeks.
Potential Traffic Impacts
13th Avenue South to be Closed During Hauling Operations - Hauling will run along 13th Avenue South and South Second Street to the river's edge on the south side of the construction site (using the entrance at 13th Avenue South and West River Parkway). Flaggers will be present while hauling is in progress, and traffic attendants will be posted at all driveways along the haul route.
Truck Traffic - There will be increased construction traffic in the vicinity of the site. Some of the streets affected include: Second Street Southeast east to 11th Avenue Southeast; Second Street Southeast to Sixth Avenue Southeast, First Street South and 19th Avenue South, Bluff Street south to 13th Avenue South, Second Street South west to 11th Avenue South.
Sidewalk/lane closures at Washington and University - The sidewalk on the north side of Washington Avenue may be closed between Seven Corners and 12th Avenue South while crews redo the curb cuts at the corners. Occasional lane closures may also be necessary during this phase of construction. Similar work will take place on University Avenue between Eighth and 10th avenues SE starting in mid-May.
Street Closures Needed at 14th Avenue South and First Street South - To allow utility relocation and widening of I-35W northbound, 14th Avenue South and First Street South (near the Seven Corners Apartments) are temporarily closed. Street parking on Second Street South and 14th Avenue is restricted to allow two-way traffic along Second Street South from 19th Avenue to the closure. Potential Noise and Light Impacts Crews are working night shifts seven days a week on both sides of the river as well as in the casting yard. Lights and construction traffic may be noticeable between 5:30 p.m. and 4 a.m.
As crews begin to relocate utilities and widen the highway on the south side of the construction site, there will be noticeable hammering as they remove the old asphalt, curbs and gutters. Back-up alarms will also be noticeable as trucks are loaded in that area.
Hammering noise will accompany falsework construction on the north side of the river. City of Minneapolis Route Planner http://www.ci.minneapolis.mn.us/traffic/routeplannerintro.asp |
| Help Spread the Word Do you know someone who would appreciate the up-to-date news, first-look pictures and detailed information you get each week? Click on the "Forward email" link at the bottom of this message to pass on a copy of this week's update with an invitation to sign up. |
Getting a Closer Look
Visit the website - The website offers up-to-date information, presentations, graphics, photos and animations, as well as interesting features on workers on the project. You can access the website at www.mndot.gov.
Hanson Blvd blast
Crosstown Blues, not so blue
Note Hwy 62 will remain open this weekend but 35W will be closed from 62 to 94.

| Crosstown: I-35W/Hwy 62 Reconstruction April 25, 2008 |
| Dear Joel Friday, This is an update on the Crosstown project. If you have questions, please do not reply directly to this email. Please visit http://www.dot.state.mn.us/projects/crosstown/ and click on "Project Contacts." |
Freeway ramp, road to close at Lyndale Avenue/Highway 62 on April 29-30
ROSEVILLE, Minn. - The exit ramp from westbound Highway 62 to Lyndale Avenue is scheduled to close from 9 p.m. to 5 a.m. on Tuesday, April 29 and Wednesday, April 30.
In addition to the ramp closure, Lyndale Avenue South at I-35W/Highway 62 is also scheduled to close during the same time frame.
The closures are needed to conduct bridge work in the area as part of the I-35/Highway 62 Crosstown reconstruction project.
Motorists should follow the posted detours routes.
I-35W and Highway 62 will remain open during closures; however, in conjunction with the bridge work, there will be a right lane closure of westbound Highway 62 at the Lyndale Ave bridge area.
For more information on the I-35W/Hwy 62 Crosstown Reconstruction project, visit www.mndot.gov or call the Crosstown Project hotline at 1-866/743-6590 or send an e-mail to crosstown@rranow.com.
Mn/DOT reminds motorists to slow down in work zones and never enter a roadway that has been blocked with barriers or cones. For statewide traffic, construction and travel information visit www.511mn.org or call 511 or log onto www.mndot.gov
35W river bridge progress
| I-35W Bridge over the Mississippi April 22, 2008 |
| Greetings! Attention: The weekly update will now be distributed at the beginning of the week instead of end of the week. If you have questions, please do not reply directly to this email. Contact Amy Barrett, Public Information Officer, at (612) 236-6901 or via e-mail at abarrett@flatironcorp.com. |
| Open House at University of Minnesota's Coffman Memorial Union The University of Minnesota Student Chapter of the American Society of Civil Engineers is hosting Mn/DOT and the Flatiron-Manson Joint Venture for an Open House this Thursday, April 24 at Coffman Memorial Union on the University of Minnesota campus. This is an opportunity for those who are interested in the project to receive updates on the bridge's progress. Thursday, April 24 Coffman Memorial Union on the University of Minnesota Campus Table on the Ground Floor, Outside of the Cafeteria and Great Hall (across Washington Avenue SE from Northrop Mall) For a map of the location go to: http://www1.umn.edu/twincities/maps/CMU/CMU-map.html Barges Arrive and Pre-Cast Segments More than Half Complete The two barges that will support the ringer crane used to place main span segments arrived at Bohemian Flats on Saturday, April 12. The barges have been moved up river and are now anchored near Pier 3 in preparation for the main span assembly. As of last week, crews had poured 61 of the 120 segments needed for the main span and expect to pour another 12 segments this week. Later this week, workers will begin hauling the pre-cast segments from the casting yard to Bohemian Flats. From that location, they will be loaded onto the barges by Bohemian Blue (the blue crane pictured below) to be transported up river to the bridge site and lifted into place by Big Ben (the red crane). This work will begin the first week in May.
|
|
Construction Update Work scheduled for the week includes:
Area residents and motorists will experience traffic issues as well as some noise and light disruptions in the coming weeks. ![]() Work continues on the south approach span of the new bridge (above). Workers are placing rebar and preparing the forms so they can continue pouring concrete during the coming weeks. Potential Noise Impacts Crews are working night shifts seven days a week on both sides of the river as well as in the casting yard. Lights may be noticeable between 5:30 p.m. and 4 a.m. Potential Traffic Impacts 13th Avenue South to be Closed During Hauling Operations - Also starting this week, crews will close 13th Avenue South for up to 10 minutes at a time, several times a day, to haul pre-cast concrete segments from the casting yard exit (at 13th Avenue South and South Second Street) to the river's edge on the south side of the construction site (using the entrance at 13th Avenue South and West River Parkway). Crews plan to transport up to six segments a day, at a rate of approximately one segment every two hours. Hauling will take place between 7 a.m. and 7 p.m. seven days a week until about June 1. Flaggers will be present while hauling is in progress, and traffic attendants will be posted at all driveways along the haul route. Sidewalk/lane closures at Washington and University - Starting this week, the sidewalk on the north side of Washington Avenue may be closed between Seven Corners and 12th Avenue South while crews redo the curb cuts at the corners. Occasional lane closures may also be necessary during this phase of construction. Similar work will take place on University Avenue between Eighth and 10th avenues SE starting in mid-May. Street Closures Needed at 14th Avenue South and First Street South - To allow utility relocation and widening of I-35W northbound, 14th Avenue South and First Street South (near the Seven Corners Apartments) are temporarily closed. Street parking on Second Street South and 14th Avenue is restricted to allow two-way traffic along Second Street South from 19th Avenue to the closure. 10th Avenue Bike Lane Closed - The bike lane on the west side of the 10th Avenue Bridge will be closed until further notice from 11 a.m. until noon on Saturdays--when the weekly Sidewalk Talks are in progress--to ensure the safety of everyone using the bridge. The City of Minneapolis has posted signs noting the restriction at each end of the bridge. Bikes and pedestrians are urged to use the lane on the east side of the bridge between 11 a.m. and noon. Truck Traffic - Trucks will be departing from the construction site regularly. Truck traffic is likely on the following routes: on Second Street Southeast east to 11th Avenue Southeast; west on Second Street Southeast to Sixth Avenue Southeast, north on Sixth Avenue and then east on University Avenue; on First Street South and 19th Avenue South; from Bluff Street south on 13th Avenue South, west on Second Street South then west on 11th Avenue South. Planning Your Route to Downtown Minneapolis - If you are planning to drive to downtown Minneapolis, you can use the links below to plan your route: City of Minneapolis Route Planner http://www.ci.minneapolis.mn.us/traffic/routeplannerintro.asp |
| Help Spread the Word Do you know someone who would appreciate the up-to-date news, first-look pictures and detailed information you get each week? Click on the "Forward email" link at the bottom of this message to pass on a copy of this week's update with an invitation to sign up. |
Getting a Closer Look
Visit the website - The website offers up-to-date information, presentations, graphics, photos and animations, as well as interesting features on workers on the project. You can access the website at www.mndot.gov.
Crosstown Blues ugly weekend 8^(
| Crosstown: I-35W/Hwy 62 Reconstruction April 22, 2008 |
| Dear Joel Friday, This is an update on the Crosstown project. If you have questions, please do not reply directly to this email. Please visit http://www.dot.state.mn.us/projects/crosstown/ and click on "Project Contacts." |
46th Street bridge to close on April 25
ROSEVILLE, Minn. - As part of the Interstate 35W/Highway 62 Crosstown reconstruction project, the 46th Street bridge is scheduled to be demolished the weekend of April 25.
To prepare for the bridge demolition, lane closures on the bridge will occur from 9:00 a.m. to 3:00 p.m. on Wednesday, April 23 and Thursday, April 24. The bridge will close at 9:00 a.m. on Friday, April 25. The 46th Street bridge is scheduled to re-open in summer 2009.
The 46th Street intersections of Stevens Ave and 2nd Ave will remain open; however, the intersections will close once bridge reconstruction impacts these areas.
The 46th Street bridge demolition and removal will occur in conjunction with a weekend closure of I-35W: all lanes of northbound I-35W, from Interstate 494 to Interstate 94, and all lanes of southbound I-35W, from I-94 to Hwy 62, will be closed at 10 p.m. Friday, April 25 through 5 a.m. Monday, April 28.
Motorists should follow the posted detours during the closure.
For more information on the I-35W/Hwy 62 Crosstown Reconstruction project, visit www.mndot.govor call the Crosstown Project hotline at 1-866-743-6590 or send an e-mail to crosstown@rranow.com.
Mn/DOT reminds motorists to slow down in work zones and never enter a roadway that has been blocked with barriers or cones. For statewide traffic, construction and travel information visit www.511mn.org or call 511 or log onto www.mndot.gov.< /p>
**************************************************************************************************************
For More Information on the Crosstown Project
Crosstown Project Hotline: 1.866.743.6590
Email: crosstown@rranow.com
Website: www.mndot.gov
Crosstown Project Office: 6242 Lyndale Ave S, Richfield*
*For office hours, call the Crosstown Project Hotline.
Crosstown Blues
Weekly Update
For the week of April 21, 2008
Public Information Events
Crosstown staff will be available to answer questions about the project at the following location:
Bachman's
6010 Lyndale Ave S, Minneapolis
Saturday, May 3, 2008
Crosstown staff available from 10:00 am to 12:00 pm
General Updates
Northbound I-35W Exit Ramp to Westbound Hwy 62/58th Street Closure: April 21 and 22
The exit ramp from northbound I-35W to westbound Hwy 62/58th Street will be closed from 9 am to 2 pm on Monday, April 21 and Tuesday, April 22. The closure of the exit ramp is needed for sheet piling removal in the area. The ramp closure is being done during daytime hours rather than at night to avoid nighttime noise activity Motorists should follow the posted detour routes. Southbound Hwy 121 with access to southbound I-35W and westbound Hwy 62 will remain open during the closures.
I-35W Closure: April 25-28
All lanes of northbound I-35W, from I-494 to I-94, and all lanes of southbound I-35W, from I-94 to Hwy 62, will be closed from approximately 10 p.m. Friday, April 25 through 5 a.m. Monday, April 28. Construction activities during this closure include the demolition of the 46th Street bridge, bridgework at 50th Street and utility work across the freeway at Diamond Lake Road and 46th Street. Motorists can use I-494, Hwy 100 and I-394 to detour around the closure.
Hwy 62 Closure: April 25-28
In conjunction with the I-35W weekend closure, Hwy 62 between Penn Ave and the western junction of I-35W is scheduled to close from 10:00 pm Friday, April 25 to 5:00 am Monday, April 28. The freeway closure is needed to conduct utility work across Hwy 62. Motorists can use Hwy 100, I-494 and Hwy 77 to detour around the closure.
46th Street Bridge to Close on April 25
The 46th Street bridge is scheduled to be demolished theweekend of April 25. To prepare for the bridge demolition, lane closures on the bridge will occur from 9 am to 3 pm on Wednesday, April 23 and Thursday April 24; and the bridge is schedule to close at 9:00 am on Friday, April 25. The 46th Street intersections of Stevens Ave and 2nd Ave will remain open; however, the intersections will close once bridge reconstruction begins to impact these areas. The 46th Street bridge is scheduled to re-open in summer 2009.
I-35W and Hwy 62 Nighttime Lane Closures
Watch for nighttime lane closures on I-35W and Hwy 62 between 9:30 pm and 6 am each night work as work continues throughout the project area. For up-to-date information on highway construction, traffic, detours and delays call 511 or go to www.511mn.org.
Freeway Ramp Closures
The following ramps are closed or tentatively scheduled to close:
Lyndale Ave
Lyndale Ave exit ramp from westbound Hwy 62 to Lyndale Ave S
Approximate closure date: Early May 2008
Approximate re-opening: September 2009
Lyndale Ave entrance ramp to eastbound Hwy 62/northbound I-35W
Status: Closed
Approximate re-opening: September 2009
Lyndale Ave exit ramp from eastbound Hwy 62 to Lyndale Ave S
Status: Closed
Approximate re-opening: September 2009
Penn Ave
Penn Ave entrance ramp to eastbound Hwy 62
Status: Closed
Approximate re-opening: July 2009
46th Street
46th Street exit ramp from southbound I-35W
Status: Closed
Approximate re-opening: October 2009
46th Street entrance ramp to southbound I-35W
Status: Closed
Approximate re-opening: October 2009
46th Street exit ramp from northbound I-35W
Status: Closed
Approximate re-opening: October 2010
46th Street entrance ramp to northbound I-35W
Status: Closed
Approximate re-opening: October 2010
66th Street
66th Street entrance ramp to northbound I-35W
Status: Closed
Approximate re-opening: June 2010
Portland Ave
Portland Ave exit ramp from eastbound Hwy 62
Status: Closed
Approximate re-opening: Fall 2008
Project Areas
Penn Ave Area
Traffic on eastbound Hwy 62 between Penn Ave and the junction of I-35W has been rerouted to travel along westbound lanes of Hwy 62. Excavation of the "old" lanes of eastbound Hwy 62 continues.
Penn Ave entrance ramp to eastbound Hwy 62: Closed
The Penn Ave entrance ramp to eastbound Hwy 62 is closed. The ramp is scheduled to reopen in July 2009.
Western Junction of I-35W and Hwy 62
Bridge work at the western junction of I-35W and Hwy 62 continues. Daytime construction activities next week include pile driving.
Northbound I-35W Exit Ramp to Westbound Hwy 62/58th Street Closure: April 21 and 22
The exit ramp from northbound I-35W to westbound Hwy 62/58th Street will be closed from 9 a.m. to 2 p.m. on Monday, April 21 and Tuesday, April 22. The closure of the exit ramp is needed for sheet piling removal in the area. The ramp closure is being done during daytime hours rather than at night to avoid nighttime noise activity. Southbound Hwy 121 with access to southbound I-35W and westbound Hwy 62 will remain open during the closures.
Hwy 121 Area
Bridge work in the area continues.
Lyndale Ave Bridge Area
Construction activities continue around the Lyndale Ave bridge area. To accommodate utility work in the area, Lyndale Ave at Crosstown will continue to be one lane in each direction through the end of April.
Lyndale Ave Freeway Ramps
§ The Lyndale Avenue exit ramp from westbound Hwy 62/southbound I-35W remains open, but is scheduled to close in early May 2008.
§ The Lyndale Ave exit from eastbound Hwy 62 is closed.
§ The Lyndale Avenue entrance ramp to eastbound Hwy 62/northbound I-35W is closed.
Soo Railroad (between Lyndale Ave S and Nicollet Ave S)
Bridge work continues.
Nicollet Ave Bridge Area
Bridge work continues.
Eastern Junction of I-35W and Hwy 62
Bridge work at the eastern junction of I-35W and Hwy 62 continues.
Portland Ave Bridge Area
Retaining wall construction activities continue.
Portland Ave exit ramp from eastbound Hwy 62: Closed
The Portland Avenue exit ramp fromeastbound Highway 62 is closed. The ramp closure is needed for crews to conduct retaining wall construction. The ramp will re-open by fall 2008.
60th Street Bridge Area
Construction activities continue around the 60th Street bridge area. Daytime construction activities next week include pile driving. 60th Street is schedule to close in the evening from 9 pm to 5am on Monday, April 21 and Tuesday, April 22. The 60th Street freeway ramps and I-35W will remain open during the closure. Motorists should follow the posted detours routes. Nighttime activities between 9 pm and 5 am will occur on Monday, April 21 and Tuesday, April 22.
Diamond Lake Road Bridge Area
The Diamond Lake Road bridge and all freeway ramps are available. However, short-term closures over the next couple of months may be needed to complete remaining work in the area. Sidewalks on Diamond Lake Road bridge remain closed and are scheduled to re-open in early summer 2008. Pedestrian access is available at 60th Street and Minnehaha Parkway.
Minnehaha Parkway Bridge Area
Bridge construction at Minnehaha Parkway and southbound I-35W continues. The construction activities will not impact traffic on I-35W.The bridge construction requires that Minnehaha Parkway be closed through April 25, 2008 (see Neighborhood Updates for more details).
50th Street Bridge Area
Reconstruction of the 50th Street bridge continues. Crews continue to remove the old bridge abutment on the west side. Construction of the new bridge abutment will begin soon; activities include excavation and sheet piling. During the I-35W closure from April 25-28, bridge beams will be set on the eastern portion of the bridge. The 50th Street bridge is tentatively scheduled to re-open in fall 2008.
46th Street Bridge Area
The 46th Street bridge is scheduled to be demolished theweekend of April 25. To prepare for the bridge demolition, lane closures on the bridge will occur from 9 am to 3 pm on Wednesday, April 23 and Thursday April 24; and the bridge is schedule to close at 9:00 am on Friday, April 25. The 46th Street intersections of Stevens Ave and 2nd Ave will remain open; however, the intersections will close once bridge reconstruction begins to impact these areas. The 46th Street bridge is scheduled to re-open in summer 2009.
46th Street Freeway Ramps: Closed
All freeway ramps at 46th Street are closed. Ramps are scheduled to re-open in 2009 and 2010.
Neighborhood Updates
Road Closures
60th Street at I-35W
60th Street at I-35W is scheduled to close in the evening from 9 pm to 5 am on Monday, April 21and Tuesday, April 22. The closure is needed to transfer fill from the southwest corner of the 60th Street bridge area to the northwest corner. The 60th Street freeway ramps and I-35W will remain open during the 60th Street closure. Motorists should follow the posted detours routes.
Minnehaha Parkway at I-35W Closure Extended
The closure of Minnehaha Parkway at I-35W has been extended until Friday, April 25. The extended closure is needed so that crews can continue to work on bridge construction near Minnehaha Parkway for the widening of southbound I-35W. Minnehaha Parkway is expected to re-open prior to the removal of the 46th Street bridge, which is tentatively scheduled for weekend of April 25. Motorists can cross I-35W at 42nd Street, 46th Street, Diamond Lake Road and 60th Street. During the closure, at least one pedestrian or bike path along Minnehaha Creek at I-35W will remain open; however, the path may be intermittently closed to safely conduct work.
Nighttime Construction Activities
Nighttime construction activities are needed in order to complete the project work within schedule and when lane closures on the freeways are allowed.The following areas are scheduled to have nighttime construction activities in the upcoming week between 10 pm and 6 am:
Hwy 62 between Penn Ave and I-35W
Activities: Excavation and utility work
Duration: April 25-28
Minneapolis
60th Street Bridge Area
Activities: Hauling of dirt
Duration: April 21 and April 22
46th Street Bridge Area
Activities: Bridge demolition and removal
Duration: April 25-28
Westbound Hwy 62 between Portland Ave and 2nd Ave
Activities: Backfilling of retaining wall
Duration: through May
Westbound Hwy 62 between Lyndale Ave and Dupont Ave
Activities: Backfilling of retaining wall
Duration: through May
Northbound I-35W between 50th Street and 46th Street
Activities: Excavation and hauling
Duration: intermittently through the summer
Southbound I-35W between 46th Street and Minnehaha Creek
Activities: Excavation and hauling
Duration: intermittently through the summer
Richfield
Eastbound Hwy 62 between Pleasant Ave and Portland Ave
Activities: Excavation and hauling
Duration: through June
Pile Driving
Daytime pile driving continues to occur throughout the project. Pile driving may occur between 6 am and 6 pm. In the upcoming week, pile driving will occur in the following areas:
Western Junction of I-35W
Duration: through early May
Minneapolis
60th Street and I-35W
Duration: through early May
Noise Wall Demolition
Existing noise walls along the Crosstown Project areas are being be taken down. Understanding the importance of the noise walls for neighborhoods, existing noise walls will be kept in place as long as possible and construction of new noise walls will be done as quickly as possible.
The following noise walls are scheduled to be removed:
Location: Along southbound I-35W near Stevens Avenue between 51st Street and Minnehaha Creek.
Approximate removal: Week of April28
Road Changes
Lyndale Ave at Crosstown
To accommodate utility work in the area, Lyndale Ave at Crosstown will continue to be one lane in each direction through the end of April.
Stevens Ave from 45th Street to 50th Street*
To facilitate construction activities, including retaining wall construction, Stevens Ave from 45th Street to 50th Street has been changed to a one-way, one lane road going south.
2nd Ave from 50th Street to 42nd Street*
To facilitate construction activities, including retaining wall construction, 2nd Ave from 50th Street to 42nd Street has been changed to a one-way, one lane road going north.
*Concrete barriers are placed in the roadway to protect residents and motorists from construction activities. The barriers will be in place until construction activities are complete. Because of the road width reduction, parking along the construction zone is not allowed.
**************************************************************************************************************
For More Information on the Crosstown Project
Crosstown Project Hotline: 1.866.743.6590
Email: crosstown@rranow.com
Website: www.mndot.gov
Crosstown Project Office: 6242 Lyndale Ave S, Richfield*
*For office hours, call the Crosstown Project Hotline.
Crosstown Blues
| From MNDOT Crosstown: I-35W/Hwy 62 Reconstruction April 14, 2008 |
| This is an update on the Crosstown project. If you have questions, please do not reply directly to this email. Please visit http://www.dot.state.mn.us/projects/crosstown/ and click on "Project Contacts." |
Weekly Update
For the week of April 14, 2008
Public Information Events
Crosstown staff will be available to answer questions about the project at the following event:
Kenny Neighborhood Meeting
Tuesday, April 15
7:00 pm
AnthonyMiddle School
5757 Irving Ave S, Minneapolis
General Updates
I-35W Closure: April 25-28
A closure of I-35W between I-94 and Hwy 62 is scheduled from 10:00 pm Friday, April 25 to 5:00 am Monday, April 28; weather permitting. Construction activities during this closure include the demolition of the 46th Street bridge, bridgework at 50th Street and utility work across the freeway at Diamond Lake Road and 46th Street.
46th Street Bridge to Close on April 25
The 46th Street bridge remains open; however, the bridge is scheduled to be demolished theweekend of April 25; weather permitting. In preparation for the bridge demolition, the 46th Street bridge will be closed at 9:00 am on Friday, April 25. The 46th Street bridge is scheduled to re-open in spring 2009.
Upcoming Hwy 62 Weekend Closure
A weekend closure of Hwy 62 between Penn Ave and the western junction of I-35W is tentatively scheduled for early May. The freeway closure is needed to conduct utility work across Hwy 62. More details to follow in upcoming updates.
I-35W and Hwy 62 Nighttime Lane Closures
Occasional nighttime lane closures on I-35W and Hwy 62 between 9:30 pm and 6 am may occur.For up-to-date information on highway construction, traffic, detours and delays call 511 or go to www.511mn.org.
Freeway Ramp Closures
The following ramps are closed or tentatively scheduled to close:
Lyndale Ave
Lyndale Ave exit ramp from westbound Hwy 62 to Lyndale Ave S
Approximate closure date: Early May 2008
Approximate re-opening: September 2009
Lyndale Ave entrance ramp to eastbound Hwy 62/northbound I-35W
Status: Closed
Approximate re-opening: September 2009
Lyndale Ave exit ramp from eastbound Hwy 62 to Lyndale Ave S
Status: Closed
Approximate re-opening: September 2009
Penn Ave
Penn Ave entrance ramp to eastbound Hwy 62
Status: Closed
Approximate re-opening: July 2009
46th Street
46th Street exit ramp from southbound I-35W
Approximate closure date: Closed
Approximate re-opening: October 2010
46th Street entrance ramp to southbound I-35W
Status: Closed
Approximate re-opening: October 2010
46th Street exit ramp from northbound I-35W
Approximate closure date: Closed
Approximate re-opening: October 2009
46th Street entrance ramp to northbound I-35W
Status: Closed
Approximate re-opening: October 2009
66th Street
66th Street entrance ramp to northbound I-35W
Status: Closed
Approximate re-opening: June 2010
Portland Ave
Portland Ave exit ramp from eastbound Hwy 62
Status: Closed
Approximate re-opening: Fall 2008
Project Areas
Penn Ave
Traffic on eastbound Hwy 62 between Penn Ave and the junction of I-35W has been rerouted to travel along westbound lanes of Hwy 62. Pavement demolition of the "old" lanes of eastbound Hwy 62 continue through the end of next week.
Penn Ave entrance ramp to eastbound Hwy 62: Closed
The Penn Ave entrance ramp to eastbound Hwy 62 is closed. The ramp is scheduled to reopen in July 2009.
Western Junction of I-35W and Hwy 62
Bridge work at the western junction of I-35W and Hwy 62 continues.
Hwy 121
Bridge work in the area continues.
LyndaleAveBridge Area
Construction activities continue around the Lyndale Ave bridge area. Daytime construction activities next week include pile driving. To accommodate utility work in the area, Lyndale Ave at Crosstown will continue to be one lane in each direction through the end of April.
Lyndale Ave Freeway Ramps
§ The Lyndale Avenue exit ramp from westbound Hwy 62/southbound I-35W remains open, but is scheduled to close in early May 2008.
§ The Lyndale Ave exit from eastbound Hwy 62 is closed.
§ The Lyndale Avenue entrance ramp to eastbound Hwy 62/northbound I-35W is closed.
Bridge Work at Soo Railroad (between Lyndale Ave S and Nicollet Ave S)
Bridge work continues.
NicolletAveBridge Area
Bridge work continues.
Eastern Junction of I-35W and Hwy 62
Bridge work at the eastern junction of I-35W and Hwy 62 continues.
PortlandAveBridge Area
Retaining wall construction activities continue.
Portland Ave exit ramp from eastbound Hwy 62: Closed
The Portland Avenue exit ramp fromeastbound Highway 62 is closed. The ramp closure is needed for crews to conduct retaining wall construction. The ramp will re-open by fall 2008.
60th Street Bridge Area
Construction activities resume around the 60th Street bridge area. Daytime construction activities next week include pile driving. Nighttime activities between 10 pm and 6am may occur for a few nights during the week of April 21. Nighttime construction activities require that 60th Street be closed (see Road Closures under Neighborhood Updates for more details).
DiamondLakeRoadBridge and Ramps Open
The Diamond Lake Road bridge and all freeway ramps are available. However, short-term closures over the next couple of months may be needed to complete remaining work in the area. Sidewalks on Diamond Lake Road bridge remain closed and are scheduled to re-open in early summer 2008. Pedestrian access is available at 60th Street and Minnehaha Parkway.
MinnehahaParkwayBridge Area
Bridge construction at Minnehaha Parkway and southbound I-35W continues. The construction activities will not impact traffic on I-35W.The bridge construction requires that Minnehaha Parkway be closed through April 18, 2008 (see Neighborhood Updates for more details).
50th Street Bridge Area
Work on the 50th Street bridge resumes. Next week, crews will remove the old bridge abutment on the west side and then begin construction of the new abutment. Pile driving in the area may begin in early May. During the I-35W closure scheduled from April 25-28, bridge beams will be set on the eastern portion of the bridge. The 50th Street bridge is tentatively scheduled to re-open in fall 2008.
46th Street Bridge Area
The 46th Street bridge remains open. Daytime construction activities next week include excavating and grading for retaining wall construction. The 46th Street bridge is scheduled to be removed the weekend of April 25; weather permitting. In preparation for the bridge demolition, the 46th Street bridge will be closed at 9:00 am on Friday, April 25. The bridge is tentatively scheduled to re-open in spring 2009.
46th Street Freeway Ramps: Closed
All freeway ramps at 46th Street are closed. Ramps are scheduled to re-open in 2009 and 2010.
Neighborhood Updates
Road Closures
60th Street at I-35W
60th Street at I-35W is tentatively scheduled to close for a few nights during the week of April 21. More details to follow in upcoming updates. The closure is needed to transfer fill from the southwest corner of the 60th Street bridge area to the northwest corner.
Minnehaha Parkway at I-35W Closure Extended
The closure of Minnehaha Parkway at I-35W has been extended until Friday, April 25. The extended closure is needed so that crews can continue to work on bridge construction near Minnehaha Parkway for the widening of southbound I-35W. Minnehaha Parkway is expected to re-open prior to the removal of the 46th Street bridge, which is tentatively scheduled for weekend of April 25. Motorists can cross I-35W at 42nd Street, 46th Street, Diamond Lake Road and 60th Street. During the closure, at least one pedestrian or bike path along Minnehaha Creek at I-35W will remain open; however, the path may be intermittently closed to safely conduct work.
Pile Driving
Daytime pile driving continues to occur throughout the project. Pile driving may occur between 6 am and 6 pm. In the upcoming week, pile driving will occur in the following areas:
Minneapolis
Northwest corner of 60th Street and I-35W
Duration: One to two days
Richfield
Southeast corner of Lyndale Ave and Crosstown
Duration: through April
Noise Wall Demolition
Existing noise walls along the Crosstown Project areas are being be taken down. Understanding the importance of the noise walls for neighborhoods, existing noise walls will be kept in place as long as possible and construction of new noise walls will be done as quickly as possible.
The following noise walls are scheduled to be removed:
Location: Along southbound I-35W near Stevens Avenue between 51st Street and Minnehaha Creek.
Approximate removal: Week of April21
Road Changes
Lyndale Ave at Crosstown
To accommodate utility work in the area, Lyndale Ave at Crosstown will continue to be one lane in each direction through the end of April.
Stevens Ave from 45th Street to 50th Street*
To facilitate construction activities, including retaining wall construction, Stevens Ave from 45th Street to 50th Street has been changed to a one-way, one lane road going south. Pavement demolition of the closed portion of Stevens Ave continues through the end of next week.
2nd Ave from 50th Street to 42nd Street*
To facilitate construction activities, including retaining wall construction, 2nd Ave from 50th Street to 42nd Street has been changed to a one-way, one lane road going north.
*Concrete barriers are placed in the roadway to protect residents and motorists from construction activities. The barriers will be in place until construction activities are complete. Because of the road width reduction, parking along the construction zone is not allowed.
Construction in full swing in Blaine
The highway 65 and county road 14 bridge project already has county 14 closed at highway 65 until late August. Detours around the area are posted to use Highway 10. That is a long way out of your way. I suggest Bunker Lake Blvd. to the north and county 12 (109th Ave) to the south.
Hanson Blvd construction in Coon Rapids and Andover will start up shortly to make Hanson a 4 lane highway from County 14 past Bunker Lake Blvd.
Content © 2009 'Frequent Contributors'. Design © 2009 ActiveRain Corp.
Logos and service marks owned by copyright holder.




